Commercial Port – Local Notice to Mariners No. 01/10

Dated 5 February 2010

Seabed works at Portsmouth Continental Ferry Port berth No2

 

  1. Notice is Hereby Given that seabed levelling and protection works will take place on berth No 2 CFP commencing on 8th February 2010.


  2. The works will involve the survey, seabed levelling, and the laying and fabrication of concrete mattresses involving divers.

  3. The seabed levelling will be conducted by the vessel "Adurni" which will display the appropriate signals from the COLREGS when conducting her operations.

  4. The works are expected to take up to 6 weeks to complete.

  5. Mariners should call "Portsmouth Harbour Radio" on VHF 11 for the latest update on progress.

  6. Cancel this notice on completion of the works, or on 31 March 2010.

Captain Rupert Taylor

Harbour Master