Commercial Port – Local Notice to Mariners No. 02/09
Dated 18 June 2009
Maintenance Dredge works at Albert Johnson Quay and approaches
- Notice is Hereby Given that maintenance dredging to remove high spots fom the berth at Albert Johnson Quay and approaches will, commence on 20th June 2009.
- The plant used will be the 22.5 metre x 9 metre spud leg back-hoe dredger "Witton Two", which will display the appropriate signals from the COLREGS when conducting her operations and will load the spoil into the barge "Split Two" or "Split Three".
- The works will be undertaken a few hours either side of low water daily and it is anticipated to take approximately 2 days to fully complete.
- Mariners should call the "Witton Two" or "Portsmouth Harbour Radio" on VHF 11 for the latest update on progress.
- Cancel this notice on completion of the works.
Captain Rupert Taylor
Harbour Master
Portsmouth Commercial Port